📋 Objectives for This Stage
- Prepare a complete and error-free submission package as per the specific municipality's requirements (e.g., Dubai Municipality, ADM)
- Compile all required architectural, structural, and MEP drawings
- Include all necessary supporting documents, NOCs, and application forms
- Submit the application through the official online portal
- Obtain an official submission reference number for tracking purposes
⚙️ Standard Operating Procedure (SOP)
-
Prepare Submission Checklist
PRO/Project Coordinator to obtain the latest submission checklist from the relevant authority's website.
Details:- Check for any recent changes in requirements
- Responsible: PRO / Project Coordinator
-
Compile Drawing Set
Combine all architectural, structural, and MEP drawings into a single PDF set, stamped and signed by all parties.
Details:- Ensure all title blocks are correct as per ACAD standards
- Responsible: Project Architect
-
Gather Supporting Documents
Collect all required documents: Title Deed, Affection Plan, consultant/contractor trade licenses, NOCs (DEWA, RTA, etc.), and appointment letters.
Details:- Scan all documents to high-quality PDFs
- Responsible: PRO / Project Coordinator
-
Online Portal Submission
PRO to log in to the municipality portal, create a new application, and upload all prepared documents.
Details:- Pay the initial submission fees online
- Responsible: PRO
-
Log Reference Number
Once submitted, log the official application reference number in the project's CRM record for tracking.
Details:- Inform the Project Architect and client that the project is 'Under Review'
- Responsible: PRO