📋 Objectives for This Stage

  • Monitor the submission status and authority review timeline
  • Manage and respond to all technical comments from reviewing departments
  • Coordinate any required revisions to drawings or supporting documents
  • Ensure all permit fees are paid and clearances obtained
  • Secure the official Building Permit to proceed with construction

⚙️ Standard Operating Procedure (SOP)

  1. Daily Status Monitoring

    PRO to check the municipality portal daily for any updates, comments, or status changes.

    Details:
    • Log all status updates in project tracking sheet
    • Responsible: PRO
  2. Review Comments Management

    Upon receiving technical comments, immediately distribute to relevant team members and schedule a response strategy meeting.

    Details:
    • Categorize comments by discipline: Architectural, Structural, MEP, Civil Defense
    • Responsible: Project Architect
  3. Coordinate Revisions

    For each comment, assign to appropriate team member and set deadline for response. Prepare revised drawings and supporting documents as required.

    Details:
    • All revisions must be reviewed by Project Architect before resubmission
    • Responsible: Design Team & Consultants
  4. Resubmission Process

    Compile all revised documents and resubmit through the portal with a detailed response letter addressing each comment.

    Details:
    • Include summary of all changes made
    • Responsible: PRO
  5. Permit Collection

    Once approval is confirmed, pay all outstanding fees and collect the official Building Permit from the municipality.

    Details:
    • Verify all permit conditions and validity periods
    • Responsible: PRO