📋 Objectives for This Stage

  • Provide continuous site supervision to ensure work complies with approved drawings and specifications
  • Manage and respond to contractor RFIs (Requests for Information) and material submittals
  • Conduct regular progress meetings and maintain comprehensive project documentation
  • Coordinate municipal inspections and ensure compliance with safety standards
  • Review and certify contractor payment applications based on completed work

⚙️ Standard Operating Procedure (SOP)

  1. Daily Site Visits

    Site Engineer to conduct daily inspections and document progress, quality issues, and safety concerns.

    Details:
    • Complete daily site report using ACAD-FORM-006
    • Responsible: Site Engineer
  2. RFI Management

    Receive, review, and respond to contractor RFIs within 48 hours. Coordinate with design team when necessary.

    Details:
    • Log all RFIs in project tracking system
    • Responsible: Project Architect
  3. Material Submittal Review

    Review all contractor material and equipment submittals for compliance with specifications and design intent.

    Details:
    • Maintain approved submittal register
    • Responsible: Project Architect
  4. Weekly Progress Meetings

    Conduct weekly site meetings with contractor, consultants, and client to review progress and address issues.

    Details:
    • Document all discussions in meeting minutes
    • Responsible: Project Architect
  5. Payment Certification

    Review monthly payment applications from contractor and certify based on actual work progress and quality.

    Details:
    • Conduct joint measurement with contractor for verification
    • Responsible: Project Architect & Site Engineer