📋 Objectives for This Stage
- Provide continuous site supervision to ensure work complies with approved drawings and specifications
- Manage and respond to contractor RFIs (Requests for Information) and material submittals
- Conduct regular progress meetings and maintain comprehensive project documentation
- Coordinate municipal inspections and ensure compliance with safety standards
- Review and certify contractor payment applications based on completed work
⚙️ Standard Operating Procedure (SOP)
-
Daily Site Visits
Site Engineer to conduct daily inspections and document progress, quality issues, and safety concerns.
Details:- Complete daily site report using ACAD-FORM-006
- Responsible: Site Engineer
-
RFI Management
Receive, review, and respond to contractor RFIs within 48 hours. Coordinate with design team when necessary.
Details:- Log all RFIs in project tracking system
- Responsible: Project Architect
-
Material Submittal Review
Review all contractor material and equipment submittals for compliance with specifications and design intent.
Details:- Maintain approved submittal register
- Responsible: Project Architect
-
Weekly Progress Meetings
Conduct weekly site meetings with contractor, consultants, and client to review progress and address issues.
Details:- Document all discussions in meeting minutes
- Responsible: Project Architect
-
Payment Certification
Review monthly payment applications from contractor and certify based on actual work progress and quality.
Details:- Conduct joint measurement with contractor for verification
- Responsible: Project Architect & Site Engineer